Road Construction Projects
The following County Trunk Highway or local road projects are proposed or in progress.
County Highway Y
Full Road Closure (E. Main Street within the City of Chilton)
Current Status | The work is set to begin on the utility portion of the project on Monday, August 28, 2023, and is expected to continue for the remainder of the construction season. |
Description | City of Chilton and Calumet County Highway Dept. will be reconstructing County Y within the City of Chilton. |
Traffic Impacts | Motorists should take caution to avoid this area and use the designated detour route listed below during this project. All access to residential and business properties will be maintained as much as feasible. Detour Route for CTH "Y" from STH 32/57 to E. Breed Street:
|
Contact | Any questions or concerns about this project should be directed to the Calumet County Highway Department at (920) 849-1434. |
County Highway X
Full Road Closure from STH 32/57 RR Tracks to the East City Limits
Current Status | The work is set to begin on Monday, June 12, 2023, and is expected to run through October weather dependent. |
Description | The City of New Holstein, Alfson Excavating LLC., and Calumet County Highway Department will be participating in the Box Culvert replacement and Road Construction. |
Traffic Impacts | Motorists should take caution to avoid this area and use the designated detour route listed below during this project. All access to residential and business properties will be maintained as much as feasible. Detour Route for CTH "X" from STH 32/57 RR Tracks to East City Limits:
|
Contact | Any questions or concerns about this project should be directed to the Calumet County Highway Department at (920) 849-1434. |
County Highway T
Full Road Closure from Honeymoon Hill Rd to CTH X
Current Status |
| |
Description | The Highway Department will be pulverizing and paving "CTH T". |
County Highway E
Full Road Closure between STH 32/57 and Long Road
Current Status | Paving is complete. Road is open for travel starting 9/1/2023. |
Description | The Highway Department will be pulverizing and paving "CTH E". |
Last updated: 9-1-2023
The following state highway projects are proposed, in progress, or recently completed.
State Highway 55
From just north of WIS 114 to just north of US 10 within the village of Harrison, Calumet County
Timeline | Project starting on Monday, July 31, is expected to finish in mid-August, depending on weather. The WIS 55/US 10 roundabout will be CLOSED from Monday, July 31 through Friday, August 11, 2023 for work within the roundabout. |
Description | This is a resurfacing-level project that includes milling and resurfacing along WIS 55 in the project work zone. Work in the roundabout located at WIS 55 and US 10 includes spot curb and gutter replacement, inlet repair, and resurfacing. Crews must close the roundabout to conduct the improvements within the roundabout. |
Traffic Impacts | WIS 55 and US 10 will be closed to traffic for 12 days to complete the work in the roundabout. The closure begins July 31 and ends August 11. The roadway will remain open with flagging operations and shoulder closures for all remaining construction. Detours:
|
Contact | Please note that our department is not doing any of the work for this project. This is a State Project. See the Northeast Region Weekly Highway Construction Update for a two-week snapshot of all construction operations and traffic impacts at https://projects.511wi.gov/weeklyupdates-ne/. |
State Highway 32/57
From County AA (Park Avenue) just north of the city of Kiel to Jordan Avenue near the city of New Holstein.
Timeline | Project starting on Monday, July 10, is estimated to take 50 days. |
Description | This is a resurfacing-level improvement. Construction includes a mill and overlay of WIS 32, and a deck overlay of the WIS 32 railroad overpass in the project work zone. Other work includes base patching in select locations, culvert and curb ramp replacement, beam guard upgrades, culvert endwall replacement, centerline rumble strips, retrofitting bridge parapet, replacing bridge expansion joints, and pavement markings. |
Traffic Impacts | WIS 32 will be closed and detoured for initial bridge work. WIS 32 will be CLOSED AND DETOURED for bridge work. The bridge is expected to be closed five weeks. Following bridge work, all other construction will be completed under flagging operations with the highway open for travel. Detour: Motorists will be directed to use County J and County HH while the bridge is closed for construction. |
Contact | Please note that our department is not doing any of the work for this project. This is a State Project. See the Northeast Region Weekly Highway Construction Update for a two-week snapshot of all construction operations and traffic impacts at https://projects.511wi.gov/weeklyupdates-ne/. |
Last updated: 7-27-202